Want to be in the loop?
subscribe to
our notification
Business News
THE GOVERNMENT HAS ISSUED THE DECREE (NO.118) TO GUIDE THE IMPLEMENTATION OF THE INVESTMENT LAW
1. New requirement for the making of a security deposit by investors to guarantee the obligation to carry out certain investment projects where land is allocated or leased by the State.
This is new and previously applied only to large infrastructure BOT type projects. It is now a general requirement where land is involved. There are some exceptions.
For example, it does not apply if: the investor secured the land via an auction and a lump sum payment has been made for the land for the entire term; the investor is selected via a tender process.
The security deposit must be paid into the bank account of the relevant licence issuing authority.
The amount is 1%, 2% or 3% of the investment capital of the relevant project depending on the size:
- 1% in respect of projects with investment capital above 1,000 billion VND;
- 2% in respect of investment projects with investment capital from above 300 to 1,000 billion VND;
- 3% in respect of projects with investment capital of up to 300 billion VND.
The amount can be reduced 25% or 50% depending on whether the project is in an 'encouraged' or 'specially encouraged' sector or geographical area per the lists attached to Decree 118.
If the investor has advanced payment for land clearance and resettlement, such amount may be set off from the deposit.
50% is returned when all land formalities and documents to enable construction to start are completed. The remaining amount is returned when the construction works are commissioned to commence operation.
The deposit will also be returned in the event of force majeure or other circumstances as agreed with the relevant licence issuing authority.
Thus, due care should be given to the negotiation of the security deposit agreement.
2. Investment protection in the event of change-in-law
If new laws contain better incentives, investors are entitled to the more favourable incentives.
If news laws are less favourable, investors may continue to enjoy incentives already granted to them.
If investors lose incentives due to change-in-law for national security, environmental protection or social reasons, they will be compensated in one of the following ways:
- damages suffered may be set off against taxes payable;
- the objectives of their projects may be changed;
- assistance may be provided to remedy the damages.
The above is a watered down version of the investment guarantee under the old law which included monetary compensation.
Investors have a 3-year limitation period from the date the new law(s) come(s) into effect to make a claim.
3. Vietnamese language documentation is required for all documents submitted to the licence issuing authority and it is the main language to carry out investment formalities.
Thus, if there are discrepancies between the Vietnamese and foreign language versions, the authorities may rely solely on the Vietnamese versions.
This is not new but often foreign investors do not pay careful attention to the Vietnamese versions.
4. Decree 118 provides for the creation of a National Information Gateway on Foreign Investment which is an electronic data information gateway for issuance and amendments of Investment Registration Certificates, for the publication and updates on laws and policies relating to foreign investment as well as for the announcements and updates on foreign investment policies.
Vietnam does not yet have a company registrar and any system to carry out company searches. This along with the creation of a National Company Registrar is long overdue.
5. The Government, for the first time, specifically states that licence issuing authorities are not allowed to request investors to provide any additional documents other than as set out in the Investment Law and Decree 118.
This will reduce the amount of discretion and delays in the licensing process.
Decree 118 also allows licence issuing authorities only one chance to request investors to amend or supplement their application files for licences.
6. Decree 118 also sets out procedures for licensing of 'conditional' foreign investment projects. Conditions may include:
- foreign ownership cap in certain types of Vietnamese companies;
- form of investment;
- scope of investment activities;
- the types of Vietnamese partners that may participate in the investment activity(ies);
- other conditions as set out in laws, decrees and treaties in which Vietnam is a signatory.
The Ministry of Planning & Investment will spell out the details of which types of projects and what conditions are attached to them.
Those holding dual Vietnamese nationalities and foreign nationalities may choose to invest as a domestic or foreign investor.
7. Decree 118 also sets out the usual details on procedures to issue and amend licences.
8. Note that a licence will be withdrawn if an investor fails to or cannot carry out the project within 12 months from the date(s) in the registered implementation schedule and has not received approval to suspend the project. A licence may also be withdrawn based on a court judgment or arbitration award. This is interesting as arguably shareholders in dispute can request a judge or arbitrator to have the investment licence withdrawn.
Decree 118/2015/ND-CP dated 12 November 2015 (valid 27 December 2015)
DN Legal, 9 December 2015 (www.daonguyenlegal.com)
Related News
REAL TEST - NOT JUST WORDS
A truly fireproof bag must prove itself through action. SentrySafe FBWLZ0 was put to the test under flames reaching 1,300-2,000°C. Constructed with 4 layers of high-quality materials — not just for marketing, but for real protection. When risks happen, what you need is reliable protection. SentrySafe FBWLZ0 – safeguarding what matters most, even in extreme conditions.
EXCLUSIVE HKBAV MEMBER OFFER DISCOUNT: 15% OFF
Eligibility: HKBAV membersPromotion: Special offer for the 2026 Mid-Autumn FestivalHow to enjoy the discount: Please mention that you are an HKBAV member when placing your order.
TECHNOLOGY ASSESSMENT IN THE CONTEXT OF INNOVATION AND GREEN TRANSFORMATION
Vietnam's new vision on strategic foreign direct investment means that the work of Vinacontrol Group in terms of technology assessment is deemed more vital than ever. Vinacontrol Group is currently one of only two organisations nationwide designated by the Ministry of Science and Technology to conduct technology assessment under Decision No.29/2023/QD-TTg, placing it at the centre of a process that increasingly determines whether an investment project can proceed, be adjusted, or be extended.
HO CHI MINH CITY OUTLINES PLANS TO START FOUR MORE METRO LINES
Ho Chi Minh City People’s Committee plans to begin construction on four metro lines by the end of 2026, which is part of the plan to complete 255km of metro lines by 2030. The first line, which connects Binh Duong New City with Suoi Tien, covers a length of over 32km, with an estimated investment of $2.18 billion. The line will pass through seven wards.
VIETNAM TARGETS 50,000 AI-SKILLED PROFESSIONALS FOR KEY SECTORS BY 2030
Vietnam is stepping up efforts to build an AI-ready workforce, targeting 50,000 skilled professionals and 10,000 advanced specialists by 2030 to strengthen strategic industries. Deputy Prime Minister Le Tien Chau signed Decision No.1528/QD-TTg, dated August 11, approving the National Programme on Artificial Intelligence Human Resource Development through 2030, with a vision to 2035.
DUNG QUẤT EZ, QUẢNG NGÃI IPS DRAW NEARLY US$19.4 BLN
The Dung Quất Economic Zone and Quảng Ngãi industrial parks have so far attracted 441 projects worth around US$19.4 billion, according to the Dung Quất Economic Zone and Quảng Ngãi Industrial Parks Authority (DEZA). The DEZA now has 350 projects run by 293 companies, employing nearly 81,700 workers, while about 20,000 additional experts, engineers and workers are building mega projects, according to data presented at a workshop marking the authority’s 30th anniversary recently.
























